A technician applying a lining coat to the inner wall of an emptied water tank
What our clients rate us

Water tank sealing in Petromin Jeddah

Petromin is a newly planned quarter built on the site of the old quarantine zone beside Jeddah refinery, and houses low-income families as part of the city's urban renewal programme. Tanks here are relatively modern but the industrial environment affects water and air quality. Moisture from the refinery, rare rainfall and airborne salts all concentrate on the tanks.

  • Potable-rated materials

    Linings and disinfectants cleared for drinking water tanks, not general-purpose products.

  • You get the downtime first

    How many hours the tank is out of service, told before we start rather than after we finish.

  • A first-draw flush

    We run the first draw off after refilling, and the tank is not handed back until the water runs clear.

  • Ground and roof tanks

    Villas, apartment blocks and premises that need a written record of each visit.

Why the job is different in Petromin

Petromin tanks were built between the 1990s and early 2000s and are now thirty years old or more. Leaks and cracks are visible in many. The method is set out in full on Water tank sealing in detail.

The first reason

Uniform housing tanks

Petromin housing was built to a standard design with identical tank sizes and specifications. Most tanks were constructed at the same time and fail in similar ways.

The second reason

Industrial environment and airborne salts

Jeddah refinery releases industrial vapours and moisture across the district. Salts and chemical gases corrode tank surfaces faster than in other areas.

The third reason

High-density population and constant water pressure

Petromin residents are dense and water use is continuous and heavy. Repeated pressure stress affects the metal base and walls.

The character of Petromin

New development: ongoing construction and vacant plots between the homes

Petromin is uniform low-income housing with high population density, and all tanks follow the same standard design. Treatment focuses on heavy use, constant pressure, and protection against external contamination from the nearby refinery.

Before treatment

What we read before any material is opened

A south Jeddah quarter adjacent to Jeddah oil refinery, built on land formerly known as Al Karantina, the old quarantine zone. Low-income housing and a main street facing the refinery perimeter fence.

A fine crack running through a concrete wall

Cracking in the wall

Cracks begin from constant water pressure, dense population and heavy daily use.

The junction of a concrete floor and wall inside an empty tank

The floor to wall joint

Pipe openings and valves in standard designs leak in similar ways and places.

A coating flaking away from a concrete surface

The condition of the old lining

The floor-to-wall joint needs special care because population pressure is continuous and unrelenting.

Limescale deposits inside a water pipe

Sediment and scale

Internal humidity is very high from constant use and steam from communal bathrooms and informal kitchens.

Water pipes passing through a concrete wall

The pipe entries

Ground foundation beneath tanks may be unstable if built on old quarantine zone soil.

A metal cover over a water tank opening

The hatch and the vent

Industrial vapours from the refinery deposit on external surfaces and cause rapid staining and cracking patterns.

How we work

  1. 1

    Inspect with the tank empty

    We drain it and read the surface dry: whether the water leaves through a crack, a joint or a pipe collar, and what the outer face of the wall and the ceiling below are telling us. A level test with the valves closed separates a leaking tank from leaking pipework.

  2. 2

    Clean and prepare the substrate

    Sediment out, a high pressure wash, the loose old lining and the weak surface layer of the concrete taken back, then dried. The material grips sound substrate and nothing else.

  3. 3

    Make the cracks and joints good

    Cracks are chased out and filled with a repair mortar, a cove is formed where the floor meets the wall, and every pipe collar is treated on its own.

  4. 4

    Lining, fill test, sterilisation

    Successive coats, each run across the one beneath it, on the face the water touches. Then a full cure, a fill with the level watched, and sterilisation with the first fill run to waste before the tank returns to use.

What water tank sealing includes

  • A technician inspecting with a flashlight

    Finding where the water leaves

    Carried out drained and dry: cracks, joints, pipe collars and the outer face of the wall.

  • A metal floor drain

    Draining and sediment removal

    The last of the water and the settled layer on the floor come out, because a lining does not stick over sediment.

  • A gloved hand applying bait into a joint

    Cracks and joints made good

    The crack opened and filled, a cove formed at the floor to wall junction, and each pipe entry worked separately.

  • A spray nozzle in close detail

    Lining coats on the water face

    More than one coat, each crossing the one below, in material made for drinking water tanks rather than roof waterproofing.

  • A clean kitchen counter after treatment

    Curing, fill test and sterilisation

    The material is left to cure, the tank is filled and the level watched, then sterilised and the first fill run to waste. How long the cure takes follows the material and the weather, and we tell you before the date so you can plan around the supply.

  • The visit report being written on a clipboard

    A follow-up level check

    We come back once it is in service to read the level and check the outer face, because any remaining loss shows up then rather than on the day of the work.

What is different about Al Jamiah Sub-Municipality

Al Jamiah sub municipality spans the older south of Jeddah. Planned districts such as Al Fayha, Al Thaghr and Madain Al Fahd sit beside crowded popular quarters like the Nazlahs and Al Quraiyat, and beside cleared or clearing land in Ghulail, Petromin and Al Thaalibah awaiting redevelopment. Apartment buildings stand close together above dense runs of shops and restaurants along Old Makkah Road and Prince Majid Road. Drainage in the popular quarters is ageing, humid air drifts in from the port and refinery side to the west, and the flat low lying ground holds rainwater in narrow streets.

Questions about this district

Are Petromin tanks worse than elsewhere because of the refinery?

Yes. Industrial environment causes faster corrosion. Vapours and airborne salts weaken the outer tank surface.

Does Petromin water need extra filters after tank sealing?

Filtration is the water company's responsibility. Tank sealing only prevents external leakage.

Most tanks were built at the same time - do we need coordinated district treatment?

It may help with planning and cost. Treating one or two first will show whether wider district action is needed.

What if refinery water has entered the tank?

If external seepage enters through cracks, full sealing stops it. Water testing may be wise before resuming drinking use.

Do residents complain of water odour from refinery proximity?

That may be external contamination seeping in. Full tank sealing protects against outside pollutants.

Do residents need to relocate during repair?

Not necessarily. We drain and repair as quickly as possible. A small tank may need only a few hours.

How much does water tank sealing in Petromin cost?

It is set after the inspection, because the price follows the type of infestation, the size of the space, how far it has spread and the number of visits it needs. Send a photo and a description on WhatsApp and we will give you an estimate before we reach Petromin.

Nearby districts we cover

Other services in Petromin

Other services we provide to residents of Petromin.

All services

Need water tank sealing in Petromin? Tell us what you saw and we will tell you what it needs

We reach Petromin at a time we agree, and you get the full cost before we start.

Call now +966 57 336 7012 WhatsApp